BETTERCOAL PRODUCER
BLACK ROYALTY MINERALS KOORNFONTEIN (PTY) LTD
PUBLIC REPORT
Read the overview
Continuous Improvement Plan (CIP) Progress
Progress in working towards meeting the provisions of the Bettercoal Code.
Continuous Improvement Plan commencement: May 2026
Figures accurate as of: June 2026
cip progress
MAY
2026
115
Total assessment findings / changes to be implemented
0
Changes implemented and independently verified
0
Changes implemented and awaiting on-site verification
115
Findings Open/ changes still to be implemented
Timeline
November 2023
LETTER OF COMMITMENT & ASSESSMENT PLANNING
Signed letter of commitment to work towards meeting the expectations of the Bettercoal Code. Completed questionnaire to allow independent assessors to plan for on-site assessment.
November 2025
on-site assessment
On-site mine assessment carried out, assessing site(s) against the provisions of the Bettercoal Code.
May 2026
CONTINUOUS IMPROVEMENT PLAN AGREED
Continuous Improvement Plan (CIP) set. The CIP supports the company in working towards meeting the expectations of the Bettercoal Code.